Bengaluru-Chennai Expressway Route Map: 4-Lane Highway Connecting Hoskote To Sriperumbudur Ready By December
The 262 km-long Bengaluru-Chennai expressway, being built at a cost of over Rs 17,930 crore, will be operational by December 2024, said BJP leader and three-time MP from the Bangalore Central constituency, PC Mohan.
The Bengaluru-Chennai Expressway (BCE) project, officially NE-7, is an under-construction 4-lane access-controlled road connecting Hoskote near Bengaluru, Karnataka, with Sriperumbudur near Chennai, Tamil Nadu. The expressway is expected to reduce travel time between the two cities to only two hours.

According to reports, the Karnataka section of the expressway is nearly completed and could soon be open to traffic. However, the sections in Andhra Pradesh and Tamil Nadu still have significant work remaining and and are far from being finished.
This greenfield project, first announced in 2011, is now being developed under the Bharatmala Pariyojana program. Prime Minister Narendra Modi laid its foundation stone on May 26, 2022.
Union Road Transport Minister Nitin Gadkari had also announced that the Bengaluru-Chennai greenfield (new) expressway will be inaugurated by Prime Minister Narendra Modi before December this year.
The 262 km-long Bengaluru-Chennai expressway is being built at a cost of over Rs 17,930 crore and will pass through the states of Karnataka, Andhra Pradesh, and Tamil Nadu. The highway will be eight lanes for a distance of 240 km, with the remainder being an elevated stretch of 22 km. Nearly 2,650 hectares of land were acquired for the project.
Bangalore - Chennai Expressway's feasibility and preliminary design report was prepared by Egis - BCEOM International - SECON in 2009. The report suggests the expressway will get saturated in 2029 (4 lane), 2037 (6 lane) and 2041 (8 lane).
This expressway was originally envisioned as an 8 lane road from the get-go, but was downgraded to 4 lanes in mid-2020 keeping the projected traffic in mind. The expressway will feature a 21 meter wide depressed median and all structures (bridges, culverts etc.) will be built up to allow for future widening to 8 lanes from the inside.
Key Specifications:
- Proposed ROW: 90m
- Proposed Carriageway: 2 x 7.5m
- Total Number of Bridges: 162
- Minor Bridges: 144
- Medium Bridges: 9
- Major Bridges: 9
- Railway Crossings: 4
- Number of Culverts: 143
- Number of Pedestrian Underpasses: 52
- Number of Vehicular Underpasses: 41
- Number of Flyovers: 17
Spurs:
Four spurs have been proposed for inclusion in the project. Spur-3 has been approved with a reduced length of 2.050 km. Spur-1 has been subsumed into the 280.8 km Bangalore Satellite Town Ring Road project.
- Spur-1 (95.63 km): KM 14 of Expressway to Dobbaspete on NH-4
- Spur-2 (3.58 km): KM 0 to NH-4 near Konadasapura (east of Bengaluru)
- Spur-3 (6.47 km): KM 50.91 to Kolar Gold Fields
- Spur-4 (7.44 km): KM 190.01 to Katpadi
- In Chennai, a 22.6 km 6-lane elevated expressway will be built from Sriperumbudur to Maduravoyal from Km 262.00 to 284.600 on NH-48 (old NH-4).
Route Map:
The route map of the expressway displays all key interchanges with other highways and roads (sourced from NHAI's tender documents).
The project is divided into 4 phases and 11 sections, all to be executed in parallel.
PHASE 1 (KARNATAKA):
Package 1 (26.40 km): Bangalore to Malur (Km 0.000 to Km 26.400)
Package 2 (27.10 km): Malur to Bangarpet (Km 26.400 to Km 53.500)
Package 3 (17.50 km): Bangarpet to Bethamangala (Km 53.500 to Km 71.000)
PHASE 2 (ANDHRA PRADESH & TAMIL NADU):
Package 1 (25 km): Bethamangala - Baireddypalle (Km 71.000 to Km 96.000)
Package 2 (31 km): Baireddypalle to Bangarupalem (Km 96.000 to Km 127.000)
Package 3 (29 km): Bangarupalem to Gudipala (Km 127.000 to Km 156.000)
PHASE 3 (TAMIL NADU):
Package 1 (24 km): Gudipala to Walajahpet (Km 156.000 to Km 180.000)
Package 2 (24.5 km): Walajahpet to Arakkonam (Km 180.000 to Km 204.500)
Package 3 (25.5 km): Arakkonam to Kancheepuram (Km 204.500 to Km 230.000)
Package 4 (32.1 km): Kancheepuram to Sriperambadur (Km 230.000 to Km 262.100)
PHASE 4 (CHENNAI, TN):
DPR Preparer: VAX Consultants - L&T Infrastructure Engineering Ltd. (JV)
Package 1 (22.6 km): Sriperumbudur to Maduravoyal from Km 262.00 to 284.600 on NH-48 (NH-4)
-
Chennai Gold Silver Rate Today, 23 March 2026: Gold Price Hits 4-Month Low, Silver Slumps Amid Market Volatily -
Dhurandhar 2 Box Office Collection Day 5: Ranveer Singh Film Surges Ahead, Targets All-Time Records -
Gold Rate Today 23 March 2026: IBJA Gold Prices Alongside Tanishq, Kalyan, Malabar, Joyalukkas -
Bangalore Gold Silver Rate Today, 23 March 2026: Gold, Silver Extend Losses Amid Strong Dollar, Fed Outlook -
Iran Rejects Trump’s Ceasefire Claim: Tehran Denies Talks, Calls It ‘US Retreat’ -
Tamil Nadu Opinion Poll: ANS Projects DMK Winning In 180 Seats In 234-Member Assembly -
Chennai Gold Silver Rate Today, 23 March 2026: Gold Price Hits 4-Month Low, Silver Slumps Amid Market Volatily -
Gold Silver Rate Today, 23 March 2026: City-Wise Prices, MCX Gold And Silver Extend March Weakness -
Passengers Evacuated After Air Canada Plane Reportedly Hits Fire Truck At LaGuardia -
Trump Announces 5-Day Strike Pause With Iran Amid Escalating West Asia War -
Oil Prices Slide, Stocks Recover Soon After Trump’s 'Ceasefire' Announcement -
Iran vs US-Israel War Halted? Breakthrough or Breather Before a Bigger Conflict












Click it and Unblock the Notifications