Gokhale Bridge Construction On Track: Full Completion Expected By Early May 2025
The construction of the Gokhale Bridge, which connects the east and west parts of Andheri, is progressing rapidly. The bridge is expected to be fully completed by the first week of May 2025, and it will be opened for traffic in the second week of May, according to a Lokmat report. The Municipal Corporation's Bridge Department is overseeing the project.
Contractors were appointed in December 2022 to reconstruct the railway section of the Gokhale Bridge, which connects C. D. Barfiwala Road and N. S. Phadke Road. However, confusion arose due to a gap between the Gokhale Bridge and Barfiwala Bridge, creating challenges for the proper connection of the two bridges.

To address this issue, there were extensive discussions at the administrative level. As the cost of the bridge increased, the help of experts from the VJTI organisation was sought. After inspecting the situation, the experts suggested some solutions, and the municipality took the necessary measures. However, this led to an increase in the overall cost of the project.
The first phase of the Gokhale Bridge was completed in February 2024, and this section opened for traffic on February 26, 2024. Currently, only light vehicles are allowed to use this part of the bridge.
The work on the railway section in the second phase has also recently been completed. Additional Commissioner Abhijit Bangar has instructed that the work on the access road within the municipal limits be finished by the end of April 2025.
While the municipality initially expected the bridge to be completed by June 2025, the progress of the work has accelerated, and it is now expected to be completed in the first week of May. The bridge will be opened for traffic in the second week of May.
-
LPG Crunch: Karnataka Brings New SOPs, Makes PNG Registration Mandatory for Businesses -
Hyderabad Gold Silver Rate Today, 30 March 2026: Check Fresh 24K, 22K, 18K Gold And Silver Prices In City -
Opinion Poll For Kerala Assembly Election 2026: Ldf Strength In Kannur And Kasaragod -
Tamil Nadu Polls 2026: Vijay Reveals Rs 645 Crore Assets, Rs 266 Crore in Banks; Know All His Declaration -
Mumbai Metro Line 9 Set for April 3 Launch, Dahisar-Mira Bhayandar to Get Direct Boost -
Trump Hints At Breakthrough With Iran Amid War Escalation, Calls Recent Move A ‘Sign Of Respect’ -
Rahul Arunoday Banerjee Autopsy Report: Actor Was Underwater For Over An Hour, Sand Found In Lungs -
West Bengal Assembly elections: Election Commission transfers heads of 173 police stations -
Delhi Weather Brings Relief: IMD Issues Yellow Alert For Rain, Thunderstorms And Gusty Winds; Check Forecast -
Tamil Nadu Elections 2026: Vijay Files Nomination Same Day as MK Stalin, Sets Up Symbolic Political Face-Off -
Too Close To Call? 57 Key Seats Could Decide West Bengal Election 2026 As TMC And BJP Gear Up For Tight Battle -
Kim Jong Un Oversees New Solid-Fuel Missile Engine Test, Claims Capability To Reach US Mainland












Click it and Unblock the Notifications