Utkal Express derailment: Was track being repaired without permission?

By Vicky
|

The probe into the tragic Utkal Express derailment has prima facie indicated that negligence could be the reason for the accident. A probe would be set up to ascertain if any maintenance work was being done on the tracks without permission.

A mangled coach of the Puri-Haridwar Utkal Express train being hauled off the tracks by a crane, at the accident site in Khatauli near Muzaffarnagar

It was not "clear" what kind of work was going on at the site, said Mohd Jamshed, Member, Traffic, Railways.

"However, any work on tracks has to follow a manual. We have maintenance manuals which lay down guidelines for work on any kind of railway infrastructure," he told the media here.

A probe will ascertain if work was being carried out on the tracks and if so, whether the rules had been followed.

    Utkal express accident: Audio clip of conversation between staff reveals truth | Oneindia News

    The probe, which will begin tomorrow, will be conducted by the Commissioner, Railway Safety, Shailesh Kumar Pathak, who will look into "every angle, be it sabotage, technical lapse or manual fault".

    Jamshed, who visited the spot in Khatauli where the accident occurred yesterday, killing 21 people, said he had seen maintenance tools on the tracks.

    "There is some audio clip of some conversation that we will probe. Also, when we did the site inspection, we saw some equipment the railways use for track repair present there." he said.

    "Whenever this kind of a big accident happens, coaches get smashed, toppled, capsized and derailed. In this case, a 200-metre track has been damaged completely. It has to be investigated in detail. All measurements are being taken and every lapse is being taken into account," Jamshed said.

    The senior officer also said the Railway Police had lodged an FIR in the case at Khatauli under Sections that included mischief causing destruction of railway property, causing death by negligence, causing grievous hurt, endangering life and personal safety.

    "Fixed infrastructure on which the rail network runs like tracks, overhead equipment and signals are regularly maintained as per schedule. Maintenance of tracks is done during operations by blocking them as per requirement, according to fixed time and schedule.

    Written permission needs to be taken for this work," he said.

    He also said sometimes repair needs to be done on an emergency basis, but even then, if the next station is informed, the consequent trains are stopped.

    "Then we get our supervisors on the track which is inspected and repaired after which the trains are allowed to run with a speed restriction. Red flags are also shown to trains in case there is a problem on the tracks," he said.

    OneIndia News

    For Daily Alerts
    Get Instant News Updates
    Enable
    x
    Notification Settings X
    Time Settings
    Done
    Clear Notification X
    Do you want to clear all the notifications from your inbox?
    Settings X
    We use cookies to ensure that we give you the best experience on our website. This includes cookies from third party social media websites and ad networks. Such third party cookies may track your use on Oneindia sites for better rendering. Our partners use cookies to ensure we show you advertising that is relevant to you. If you continue without changing your settings, we'll assume that you are happy to receive all cookies on Oneindia website. However, you can change your cookie settings at any time. Learn more