Lower Subansiri project incurring daily loss of Rs 10 crore

The 2000-MW project in the Subansiri river, the largest in the country and being executed by the NHPC, has run into rough weather after the work for the project came to a halt in December, 2011.
The height of the dam was initially planned for 257 metres, but later it was reduced to 116 metres after the anti-dam activists under the banner of Krishak Mukti Sangram Samiti in Assam protested. The protesters, led by KMSS president Akhil Gogoi, contend that the dam will have adverse impact on the people living downstream and the flora and fauna.
"We are incurring a loss of Rs three crore per day as the machines and other equipment are lying idle and have already started rusting. The project, which was supposed to be commissioned in March, this year, is incurring a loss of another Rs seven crore per day against revenue generation," Executive Director of the project Rakesh told a group of visiting journalists.
Already more than 55 per cent work of the project has been completed including tunnel, dam, power house and other civil work. Machines could be seen lying scattered at the project site while most of the workers have been withdrawn from the project site following suspension of work since 2011.
Though the initial estimated cost of the project was Rs 6,285 core (2002-2005), the project authority has already invested Rs 6,600 crore. The cost of the project now has gone up by Rs 1,200 crore. Beside this, there was a recurring expenditure of Rs 50 crore per month.
"Any more delay will further escalate the cost of the project which will ultimately affect the people in terms of higher cost of electricity as the continuing delay is only adding to the final cost of power," Rakesh pointed out.
He said the apprehension expressed by the anti-dam protesters were ill-founded since it was by no means a mega dam project, but a run-of-the river project with small reservoirs where 10 per cent of the rain water would be stored while the rest would flow downstream.
PTI
-
Gas Supply Squeeze May Leave 10 Lakh Bengaluru PG Residents Without Daily Meals -
Gold Silver Rate Today, 10 March 2026: City-Wise Prices Edge Lower While MCX Gold And Silver Stay Range-Bound -
Hyderabad To Get Faster Road Link To Indore As New Highway Nears Completion, Opening Likely This Month -
Hyderabad Gold Silver Rate Today, 10 March 2026: Gold, Silver Slip In Local Market; MCX Also Trades Lower -
Oil Slumps 6% As Trump Claims Iran War Will Be Over 'Ahead of Schedule' -
Pune Gold Rate Today For 18K, 22K, 24K For Rates March 2026 -
Bangalore Gold Silver Rate Today, March 10, 2026: Gold and Silver Prices Go Up -
IPL 2026 Schedule Announcement On March 12: BCCI to Release First 20 Days of Indian Premier League Fixtures -
IPL 2026 Playing XI Prediction: CSK, MI, RCB, KKR, PBKS, GT, LSG, DC, RR, SRH Impact Sub & Full Team List -
Chennai Hotels Warn of Shutdown In 2 Days As LPG Supply Crunch Hits TN -
Trisha Shouldn't Have Attended The Event With Vijay: Parthiban -
Pakistan Facing Oil Crisis? PM Orders Shutdown Of Schools And Universities, Introduces 4-Day Workweek












Click it and Unblock the Notifications