Chennai Metro Update: Purasaiwalkam To Kellys Metro Tunnel Work Set to Start, Part Of Phase-2 Expansion
Tunneling work for the Chennai Metro's Phase-2 project is expected to begin in the bustling shopping district of Purasaiwalkam by the end of August, The Times Of India reported.
The project includes the construction of a tunnel from Purasaiwalkam Metro Station on Purasaiwalkam High Road to Kellys Metro Station, as part of the 45.4 km Corridor-3 stretching from Madhavaram Milk Colony to Siruseri Sipcot. This corridor is a segment of the larger 116.1 km Phase-2 expansion.

Officials told the daily that the launch shaft, including the base slab for the tunnel boring machine (TBM), is now complete. Purasaiwalkam and Kellys stations, located approximately 700 meters apart, will soon be connected.
"The main components of the TBM are being lowered into the shaft and assembled. Following a series of tests, tunneling is expected to commence around August 25," an official stated. The Phase-2 project, consisting of three corridors, is slated for staged openings between 2025 and 2028.
The preparation for this phase encountered major challenges, particularly in relocating underground utilities in the densely populated Purasaiwalkam area. Over 18 months were spent rerouting pipelines and electrical cables to clear the way for the tunnel.
Once operational, the Purasaiwalkam station will offer direct connectivity to commuters from Madhavaram, Lighthouse, and Sholinganallur, making it easier for them to access the popular shopping destination. However, passengers from Villivakkam, Alandur, and Medavakkam may need to transfer at Alapakkam and Lighthouse stations to reach Purasaiwalkam.
Tunneling began earlier this year between Panagal Park in T Nagar and Kodambakkam. Work on extending the line from Panagal Park to Nandanam is anticipated to start in about a year. Sholinganallur, situated in Chennai's rapidly growing OMR area, is set to become a major metro hub within two years. It will feature interchange stations and a grade separator to enhance traffic flow. The OMR line, part of the Madhavaram Milk Colony-Siruseri Sipcot corridor, is expected to be completed by the end of 2026, though progress has been slightly delayed due to design modifications at key junctions.
-
Bangalore Gold Silver Rate Today, 23 March 2026: Gold, Silver Extend Losses Amid Strong Dollar, Fed Outlook -
Iran Rejects Trump’s Ceasefire Claim: Tehran Denies Talks, Calls It ‘US Retreat’ -
Tamil Nadu Opinion Poll: ANS Projects DMK Winning In 180 Seats In 234-Member Assembly -
Chennai Gold Silver Rate Today, 23 March 2026: Gold Price Hits 4-Month Low, Silver Slumps Amid Market Volatily -
Gold Silver Rate Today, 23 March 2026: City-Wise Prices, MCX Gold And Silver Extend March Weakness -
Passengers Evacuated After Air Canada Plane Reportedly Hits Fire Truck At LaGuardia -
Trump Announces 5-Day Strike Pause With Iran Amid Escalating West Asia War -
Oil Prices Slide, Stocks Recover Soon After Trump’s 'Ceasefire' Announcement -
Iran vs US-Israel War Halted? Breakthrough or Breather Before a Bigger Conflict -
Hyderabad Gold Silver Rate Today, 23 March 2026: Check Latest Gold And Silver Prices In The City -
Why Share Market Crashing Today: ₹13 Lakh Crore Wiped Out in Just 1 Hour, What Triggered Panic? -
“Thank You, India”: Iran Thanks Kashmir For Donations Of Gold, Cash And Livestock












Click it and Unblock the Notifications