Chennai-Bengaluru Expressway Status: Check Progress Report & Completion Dates Of Karnataka, AP, TN Sections

Recent updates indicate that the Chennai-Bengaluru Expressway will miss its initial December 2024 deadline, with the inauguration now anticipated in 2025.

Union Minister of Road Transport and Highways, Nitin Gadkari, confirmed in Parliament that the project will not meet the planned timeline, according to a report by The Times of India.

Bengaluru-Chennai Expressway Update

The expressway, spanning 262 kilometers, is designed to cut travel time between Chennai and Bengaluru to just 120 minutes. The expressway will also reduce the physical distance between the two cities by 38 kilometers, promising a streamlined commute at speeds of up to 120 km/h.

All three packages in Karnataka, totaling 71 km, are complete except for some minor bridge work. However, progress in Andhra Pradesh (85 km) and Tamil Nadu (106 km) has been slower, according to a report on the Swarajya website.

However, story has also highlighted the current status of the project's progress:

Karnataka Packages: The three packages in Karnataka, totaling 71 km, are largely completed, with only minor bridge work pending. The completed sections are:

  • Package 1: 26 km from Hoskote to Malur, managed by Dilip Buildcon.
  • Package 2: 27 km from Malur to Bangarpet, also handled by Dilip Buildcon.
  • Package 3: 18 km from Bangarpet to Betamangala, undertaken by KCC Buildcon. Each package is at 99% completion.

Andhra Pradesh Packages: Progress varies:

  • Package 1: 25 km from Betamangala to Baireddypalle, managed by Montecarlo, is 65% complete, with a projected finish date of March 31, 2025.
  • Package 2: 31 km from Baireddypalle to Bangarupalem, overseen by APCO Infratech, is at 45% completion, expected by March 31, 2025.
  • Package 3: 29 km from Bangarupalem to Gudipala, run by Dilip Buildcon, is 74% complete, also targeted for March 31, 2025.

Tamil Nadu Packages: Progress is mixed:

  • Package 1: 24 km from Gudipala to Walajahpet, managed by Montecarlo, is 62% complete, expected by December 31, 2024.
  • Package 2: 25 km from Walajahpet to Arakkonam, led by KCC Buildcon, is 78% complete, projected for November 30, 2024.
  • Package 3: 26 km from Arakkonam to Kancheepuram, undertaken by DP Jain & Co., is at 51% completion, targeted for March 31, 2025.
  • Package 4: 32 km from Kancheepuram to Sriperambadur, managed by Ramalingam Construction, is 61% complete, expected by February 28, 2025.

Six-Laning NH4 (Sriperumbudur-Maduravoyal): This 23 km stretch is 99% complete, with an expected finish date of August 31, 2024.

Maduravoyal-Chennai Port Elevated Expressway: The 20 km elevated expressway is only 1% complete, with an anticipated completion by May 20, 2026.

Overall, while significant progress has been made, the Bengaluru-Chennai Expressway is expected to become fully operational by August 2025, with various sections and additional projects advancing on their respective timelines.

Notifications
Settings
Clear Notifications
Notifications
Use the toggle to switch on notifications
  • Block for 8 hours
  • Block for 12 hours
  • Block for 24 hours
  • Don't block
Gender
Select your Gender
  • Male
  • Female
  • Others
Age
Select your Age Range
  • Under 18
  • 18 to 25
  • 26 to 35
  • 36 to 45
  • 45 to 55
  • 55+