The Bengaluru tunnel road project from Silk Board to Hebbal has hit another hurdle, with a Geological Survey of India (GSI) expert panel flagging concerns over the proposed construction near Lalbagh.

The panel has submitted its report to the Karnataka High Court, recommending that the tunnel design, geological conditions and construction plan be looked at again before work moves ahead.

AI Summary

AI-generated summary, reviewed by editors

The Geological Survey of India flagged concerns to the Karnataka High Court about Bengaluru's tunnel road project near Lalbagh, recommending reassessment of the design and Shaft-4's location due to risks of excavation vibrations impacting geological fractures and heritage structures.
Silk Board-Hebbal Tunnel Road GSI Flags Rock Fracture Risks Near Lalbagh

At the heart of the concern is Shaft-4, which is proposed close to the Lalbagh geological monument. The panel has pointed to existing fractures in the rock and warned that vibrations from excavation could potentially worsen them.

The report does not say that construction will definitely damage Lalbagh. Instead, it calls for a closer assessment of the risks and greater caution while deciding how the work should be carried out.

The proposed construction of Shaft-4 could involve a drill-and-blast method, where explosives are used to break through the rock. The GSI has raised concerns about the vibrations this process could generate, given the existing cracks in the geological formation.

If those fractures were to widen, the stability of some portions of the rock could be affected. The panel has also noted that underground water movement and pressure could play a role in how the fractured rock behaves.

There are concerns beyond the geological formation as well. The GSI has pointed to the possibility of construction activity affecting heritage structures in the vicinity, including the Kempegowda Tower.

The location of Shaft-4 has come under particular scrutiny because of how close it is to the Lalbagh geological monument.

The tunnel project requires shafts at various locations to facilitate the movement and operation of the Tunnel Boring Machine (TBM) underground. But the GSI panel has suggested that the proposed location of Shaft-4 should undergo another technical examination.

It has recommended that an independent technical committee assess the site and explore whether the shaft can be moved as far away from the geological monument as practically possible.

The recommendation comes down to reducing the risk before excavation begins rather than waiting to see how the rock responds once construction is underway.

The rock beneath and around Lalbagh already has naturally occurring fractures. Their presence alone does not mean the formation is unstable, but construction activity can introduce additional stresses through vibrations and changes in underground conditions.

That is why the GSI has called for a closer study of the site before the proposed excavation and blasting work is taken up.

The panel has also sought a review of the construction methods being considered for the tunnel in the area, along with a more detailed understanding of the underground geological conditions.

The possible impact on Lalbagh had earlier been raised by Bengaluru South MP Tejasvi Surya, who objected to the tunnel road project and sought an expert assessment of the geological conditions.

The matter reached the Karnataka High Court, following which a GSI expert committee was asked to study the concerns.

The panel has now submitted its findings to the court.

Notifications
Settings
Clear Notifications
Notifications
Use the toggle to switch on notifications
  • Block for 8 hours
  • Block for 12 hours
  • Block for 24 hours
  • Don't block
Gender
Select your Gender
  • Male
  • Female
  • Others
Age
Select your Age Range
  • Under 18
  • 18 to 25
  • 26 to 35
  • 36 to 45
  • 45 to 55
  • 55+