Shivarama Karanth Layout: Pending Works to Be Finished in 3 Months, Says BDA
The Bangalore Development Authority (BDA) has set a three-month deadline for engineers to complete pending road construction, pipeline installation, and other essential works in the much-awaited Dr. Shivarama Karanth Layout.
The layout, divided into nine sectors, has seen partial progress. While 50% to 60% of work is complete in different sectors, key infrastructure such as main roads and water and sewage pipelines remain unfinished. Streetlights have been installed in some areas, but 40% of the overall work is still pending. The deadline aims to ensure all necessary developments are completed within three months.

High Demand for Plots in Dr. Shivarama Karanth Layout
Dr. Shivarama Karanth Layout, located in North Bengaluru, is highly sought after, especially since BDA had not developed any new layouts after Kempegowda Layout. However, several issues, including land acquisition disputes, have delayed the project. Allegations that plots were allocated without resolving legal concerns led to a temporary halt in notifications. The matter remains in court, and once an order is received, BDA will be responsible for providing the required infrastructure to allot the plots.
Over 30,000 Plots Available
The layout consists of over 30,000 plots, of which 16,000 to 17,000 will be given to farmers who contributed land for the project. Among these, around 4,000 are corner plots, and 3,000 are on sloping terrain. The remaining 7,000 to 8,000 plots will be available to the public.
The demand for plots has driven up prices significantly, with land rates in the layout now reaching ₹4,900 per square foot-twice as high as previous BDA layouts.
Plot Allocation to Begin After Court Clearance
BDA President N.A. Harris stated that most work in the layout is complete, with only minor tasks remaining. He assured that these pending works will not delay plot allocation and that applications will be invited as soon as the court gives its approval.
With the deadline in place, Bengaluru residents eagerly await the completion of the layout, which is expected to provide much-needed residential plots in the city's northern region.
-
Bengaluru's Satellite Town Ring Road: Hoskote To Tamil Nadu Border Set To Open By June 2026 -
Bengaluru Rain: April Showers Likely in Next 12-24 Hours, Thunderstorm Chances at 35–40% -
Bengaluru Auto Strike on April 10? Long Queues At Re-Filling Stations, LPG Bunk Shut, Drivers Struggle -
Court Turns Down Bail for Bengaluru Doctor Accused of Killing Wife With Propofol Overdose -
Gorakhpur Development Authority Brings Major Relief For Plot Buyers With New Costing Policy -
Congress Manifesto for TN Assembly Elections 2026, Rahul Gandhi Missing from Campaign -
₹2,000 Monthly Aid, 3 Lakh Jobs in 300 Days: Congress’ Big Poll Promises In Tamil Nadu -
Nirmala Sitharaman Approves Rs 2,534 Crore Amaravati Projects, Clearing Secretariat And Employee Housing Plans -
Bhim Jyoti Utsav 2026 in Delhi marks B R Ambedkar anniversary with 6,000 Jai Bhim lamps -
Amit Shah Unveils BJP’s ‘Sankalp Patra’ For Bengal Polls, Promises UCC And ₹3,000 Aid For Women -
DA Hike 2026 Announcement Likely in Second Week of April, 2% Increase to 60% Expected -
Karan Adani Announces ₹33,000 Crore Investment in Odisha, Launches Key Industrial Projects












Click it and Unblock the Notifications