Namma Metro Phase 3: Double Decker Corridor May Be Shortened, BMRCL May Need Fresh Tenders
The proposed double decker corridor under Namma Metro Phase 3 could be cut short as the Karnataka government waits for the Centre's approval. The move could also force BMRCL to revisit the tenders already floated for the work.
Namma Metro Phase 3 covers 44.65 km across two corridors: the 32 km Kempapura to JP Nagar Phase 4 route along the Outer Ring Road and the 12 km Hosahalli to Kadabagere route along Magadi Road. The project has an estimated cost of Rs 15,611 crore. The Karnataka government approved it in 2022, while the Union government gave its approval in August 2024. Prime Minister Narendra Modi laid the foundation stone in August 2025, but construction has not yet begun.
AI-generated summary, reviewed by editors

The state has proposed a double decker stretch of around 37 km along the two corridors, allowing Metro trains and road traffic to run on different levels of the same alignment. Karnataka has also offered to bear around Rs 9,700 crore of the cost from its own resources.
However, the double decker proposal is yet to receive clearance from the Centre.
Why is the Centre delaying approval?
The main concern is the financial viability of the Metro project.
One argument being considered is that adding more road space through a double decker corridor could encourage greater use of private vehicles. If that happens, Metro ridership could take a hit, affecting the Namma Metro's revenue.
The proposed double decker arrangement has also affected the project's Economic Internal Rate of Return (EIRR). It is understood that the EIRR has fallen below the prescribed 14% level.
These concerns are believed to be among the reasons for the delay in getting clearance from the Centre.
Double decker stretch could come down
The double decker corridor may not be as long as the 37 km proposed by the Karnataka government.
The Phase 3 project already approved includes around 3 km of double decker flyovers at two important junctions.
About 1.4 km has been proposed at the Kanakapura Road and Outer Ring Road junction, while another 1.6 km is planned at Kamakya junction.
Another 8 km of double decker infrastructure has been proposed at major traffic bottlenecks, including Goraguntepalya.
If the Centre's approval is limited to the components included in the approved project, the double decker stretch could be reduced by around 11 km.
What happens to the tenders?
BMRCL had invited tenders in three packages in January last year for the proposed 37 km double decker corridor.
The tenders, however, were not opened because the Centre's approval was still pending.
If the length or design of the double decker corridor changes, BMRCL may have to cancel the existing tenders and invite fresh ones, according to a BMRCL official.
That could further delay work on the project.
The delay comes at a time when Bengaluru has not seen a new Metro project implemented by BMRCL in nearly four and a half years.
The KR Puram to Kempegowda International Airport Metro extension was the last major project to receive approval from the Centre. Its foundation stone was laid in 2022.
Since then, Phase 3 and the proposed Phase 3A corridor between Hebbal and Sarjapur have remained pending at different stages.
The revised Detailed Project Report for Phase 3A is also awaiting approval from the Centre.
Karnataka Deputy Chief Minister D.K. Shivakumar has been pushing for the double decker model, saying it is important for Bengaluru's traffic management.
His argument is that the city can add road capacity without acquiring large amounts of land by building the Metro and road corridors together.
Shivakumar has also expressed disappointment over the delay in getting the Centre's approval.
For Bengaluru, the issue is now not just about the 37 km double decker proposal. Any change to its length or design could affect the existing tenders and further push back work on the Phase 3 corridors.