Bengaluru Metro Pink Line: Kalena Agrahara To Tavarekere Route Set For Another Delay, Late August Launch Now
The wait for Bengaluru Metro's Pink Line connecting Kalena Agrahara to Tavarekere is likely to get a little longer now with the 7.5-km elevated corridor now expected to miss its August 15 opening target. The revised date comes as signalling clearances are still pending.
The elevated stretch between Kalena Agrahara and Tavarekere is now expected to become operational only in late August or early September. The delay of the project has been linked to pending final certification of the signalling system, a prerequisite for the mandatory safety inspection, The Deccan Herald reported.
AI-generated summary, reviewed by editors

The Research Designs and Standards Organisation (RDSO) is expected to issue the Interim Speed Certificate (ISC) within the next few days. However, the Independent Safety Assessment (ISA) certificate for the signalling system could take longer, potentially delaying the commissioning of the corridor, the DH reported.
The elevated stretch between Kalena Agrahara and Tavarekere spans 7.5 km and comprises six stations. Among them, Jayadeva Hospital will serve as a key interchange with the Yellow Line. Once the section becomes operational, Bengaluru Metro's network will expand to 103.6 km, the report noted.
Most of the physical work on the elevated corridor has already been completed. Civil construction, track laying and station finishing are largely over, while six trainsets designated for the Pink Line have already been delivered.
The trains have also successfully completed oscillation trials and Emergency Braking Distance (EBD) tests conducted by the RDSO between April 28 and May 9. These trials assess the trains' maximum operating speed and braking performance before the Interim Speed Certificate is issued.
The report added that the testing phase has now been completed and the certificate is expected shortly.
ATO Validation Still In Progress
The next major milestone is securing the Independent Safety Assessment (ISA) from Bengaluru-based Jodova Technologies Pvt Ltd.
As part of the assessment, experts will evaluate the Metro's signalling system and its integration with other technologies, including Automatic Train Protection (ATP) and Automatic Train Operation (ATO).
While ATP-related testing has already been completed, validation of the ATO system is still under way. This stage verifies whether trains can operate automatically, stop accurately at stations and achieve precise platform alignment after station-specific calibration.
According to the publication, the signalling software is currently being upgraded before being installed on the trains. Testing is scheduled between August 3 and August 5, while the ISA assessment is expected to be carried out on August 5 and August 6.
CMRS Inspection Likely In Third Week Of August
After obtaining the ISA certificate, the Bangalore Metro Rail Corporation Limited (BMRCL) will apply for the mandatory inspection by the Commissioner of Metro Railway Safety (CMRS).
During the inspection, the CMRS will examine the rolling stock and inspect facilities at the Kothanur depot, including the washing plant, underframe water-jet cleaning system, train-lifting pit jacks and other maintenance infrastructure.
The report further stated that the inspection is likely to take place during the third week of August. Any observations made by the safety commissioner will need to be addressed by BMRCL before passenger services can commence.
It added that the remaining approvals and inspections are expected to push the opening of the elevated Pink Line stretch beyond the August 15 target, making late August or early September the more likely launch window.
While work on the elevated corridor is nearing completion, construction of the 13.75-km underground section between Dairy Circle and Nagawara continues as planned. The underground stretch is currently scheduled to open in March 2027.
Once the entire Pink Line is operational, it is expected to significantly improve connectivity across Bengaluru while providing an important interchange with the Yellow Line at Jayadeva Hospital.