Teesta five to be commissioned in six to seven months

Written by: Staff
|

Gangtok, Nov 20 (UNI) The Teesta stage five hydro-electric project in Sikkim will be commissioned in six to seven months, Union Power Secretary R V Shahi has said.

Mr Shahi, who is here on a two-day visit to the state told newsmen here last night, that three units of the 510 mw project are ready.

The schedule of the project with 18km of head race tunnel, one of the longest in the country was delayed due to the landslides during the last monsoon.

Serious geological problems also delayed the construction of the project by 8 to 10 months, he said.

"Now we are constantly reviewing the project and the work is in progress. We hope to commisson the project in six to seven months," he said.

UNI BD BA KLC1433

For Daily Alerts

For Breaking News from Oneindia
Get instant news updates throughout the day.

Notification Settings X
Time Settings
Done
Clear Notification X
Do you want to clear all the notifications from your inbox?
Settings X
X
We use cookies to ensure that we give you the best experience on our website. This includes cookies from third party social media websites and ad networks. Such third party cookies may track your use on Oneindia sites for better rendering. Our partners use cookies to ensure we show you advertising that is relevant to you. If you continue without changing your settings, we'll assume that you are happy to receive all cookies on Oneindia website. However, you can change your cookie settings at any time. Learn more