GSWSS scheme to be completed by December, 2006

Written by: Staff
|

Shillong, Jun 29 (UNI) Public Health Engineering (PHE) Minister Prestone Tynsong told the state Assembly today that the Greater Shillong Water Supply Scheme (GSWSS) is expected to be completed by December 6.

The Minister was replying to a question by Sengman R Marak, who wanted to know the progress of the scheme and escalation of cost from that of original estimate of Rs 2390 lakh.

The Minister had stated that the cost jacked up almost four times from Rs 2390 lakh to 9503,77 lakh.

He informed that it was increased due to phase II scheme of GSWSS later.

The scheme, which began in 1992, would be completed by December.

To another question by Manas Choudhuri (IND), the Minister said the designed requirement of water was 135 lt per capita per day.

The Minister had informed the House that at present 9 million gallon of water was required to meet the demand, but it could manage only 6.4 million gallon.

Efforts were on to meet the shortage of water supply to the whole of greater Shillong.

UNI BS SJC RN1732

For Daily Alerts
Get Instant News Updates
Enable
x
Notification Settings X
Time Settings
Done
Clear Notification X
Do you want to clear all the notifications from your inbox?
Settings X
We use cookies to ensure that we give you the best experience on our website. This includes cookies from third party social media websites and ad networks. Such third party cookies may track your use on Oneindia sites for better rendering. Our partners use cookies to ensure we show you advertising that is relevant to you. If you continue without changing your settings, we'll assume that you are happy to receive all cookies on Oneindia website. However, you can change your cookie settings at any time. Learn more