Mumbai-Goa Highway Set For Phased Completion By 2025, Government Assures
The Union government has informed the Lok Sabha that the Mumbai-Goa National Highway (NH-66) will be completed by September 2025. Union Minister for Road Transport and Highways, Nitin Gadkari, gave this update on Thursday, according to a Hindustan Times report.
He explained that the project had been delayed due to land acquisition problems, other pre-construction activities, and financial issues faced by some contractors. However, he added that most of these issues have now been resolved with the help of the Maharashtra state government, and the remaining work is currently underway.

Gadkari shared details of specific flyovers that faced delays:
1. The Lanja and Pali flyovers were held up because of land acquisition issues.
2. The Chiplun flyover was delayed after one of its spans collapsed.
According to the minister, land-related problems for Lanja and Pali flyovers have now been settled. The Chiplun flyover's design was revised following the accident. Construction on all three flyovers is ongoing and will be completed in phases by September 2025.
He also spoke about another stretch - the Shastripul-Bahwandi-Sangameshwar-Nivli road, part of the Aravali to Talekante section. This work was also delayed due to similar land and contractor-related issues. So far, 30.68 km out of 39.24 km of this section has been completed. The remaining part will also be finished in phases by September 2025.
Gadkari was replying to a question from Narayan Tatu Rane, a BJP MP and former Chief Minister of Maharashtra, who asked about the slow pace of work.
In response to another question by Tanuj Punia, a Congress MP from Uttar Pradesh, Gadkari revealed that 683 national highway projects that began after April 1, 2014, are still incomplete. These projects have missed their original deadlines.
He said the main reasons for these delays are:
1. Land acquisition issues
2. Delays in getting permissions and clearances
3. Shifting of utilities like water and power lines
4. Encroachments
5. Law and order problems
6. Financial difficulties faced by contractors
7. Poor contractor performance
8. Natural disasters like floods, landslides, cyclones, and the COVID-19 pandemic
The minister assured the House that efforts are being made to resolve these problems and finish the projects as soon as possible.
-
Gold Rate Today 31 March 2026: Latest IBJA Benchmark And Tanishq, Kalyan, Malabar, Joyalukkas Rates -
Gold Rate Today 30 March 2026: IBJA Benchmark Rates, Tanishq, Kalyan, Malabar, Joyalukkas Prices -
Gold Silver Rate Today, 30 March 2026: City-Wise Prices, MCX Update On 24K Gold, 22K Gold And Silver -
LPG Crunch: Karnataka Brings New SOPs, Makes PNG Registration Mandatory for Businesses -
Hyderabad Gold Silver Rate Today, 30 March 2026: Check Fresh 24K, 22K, 18K Gold And Silver Prices In City -
Opinion Poll For Kerala Assembly Election 2026: Ldf Strength In Kannur And Kasaragod -
Tamil Nadu Polls 2026: Vijay Reveals Rs 645 Crore Assets, Rs 266 Crore in Banks; Know All His Declaration -
Mumbai Metro Line 9 Set for April 3 Launch, Dahisar-Mira Bhayandar to Get Direct Boost -
Hyderabad Gold Silver Rate Today, 31 March 2026: Gold And Silver See Fresh Movement, Check Latest City Rates -
Gold Silver Rate Today, 31 March 2026: City-Wise Prices, MCX Trend As Gold Rises And Silver Slips -
Rahul Arunoday Banerjee Autopsy Report: Actor Was Underwater For Over An Hour, Sand Found In Lungs -
Thunderstorm Warning In Delhi NCR: IMD Issues Orange Alert Amid Sudden Weather Shift












Click it and Unblock the Notifications