Surveys for new railway projects
New Delhi, July 23(ANI): Union Minister of State for Ministry of Railways K.H. Muniyappa on Thursday said that during the last three years, 116 surveys for new lines, 16 surveys for gauge conversion and two surveys for flyovers have been completed.
In a written reply to the Lok Sabha, Muniyappa further stated that out of the completed surveys, government has sanctioned 18 new lines, six gauge conversion and one flyover projects.
The minister also highlighted that normally, it takes around one to two years for a survey to be completed depending upon length of the line and geographical conditions. (ANI)
More From
-
Gold Silver Rate Today, 9 March 2026: City-Wise Prices, MCX Gold and Silver Ease Slightly After Rally -
Chinese Spy Ship Liaowang-1 Spotted Near Oman: Why Its Presence Near Oman Is Concerning For US Military -
Pune Gold Rate Today: Check Gold Prices For 18K, 22K, 24K in Pune -
Bangalore Gold Silver Rate Today, March 9, 2026: Gold and Silver Prices Fall as US Dollar Strengthens -
Who Is Nishant Kumar: Education, Personal Life and Possible Political Role -
Ind Vs NZ T20 World Cup Phalodi Satta Bazar Prediction: Know Who Will Win In India vs New Zealand Final -
Vijay-NDA Alliance On Cards? Pawan Kalyan Reportedly Reaches Out to TVK Chief -
Who Was Mojtaba Khamenei’s Wife Zahra Haddad-Adel and What Do We Know About Her? -
Trisha Hits Back at Parthiban: 'Crude Words Say More About the Speaker' -
India vs New Zealand T20 World Cup 2026 Final: Five Positive Signs Favouring India Before Title Clash -
IND vs NZ Final Live: When and Where to Watch India vs New Zealand T20 World Cup 2026 Title Clash -
Ind vs NZ T20 World Cup 2026: New Zealand Needs 256 Runs To Beat India And Win The World Cup












Click it and Unblock the Notifications