For Quick Alerts
ALLOW NOTIFICATIONS  
For Daily Alerts
Oneindia App Download

Chhotu Ram plant unit to be shut to install new equipment

By Staff
|
Google Oneindia News

Yamunanagar, Apr 27 (UNI) The first unit of 300 MW of Deen Bandhu Chhotu Ram thermal Power Plant here was shut down today for about three weeks.

A spokesman said here today that the shut down is essential to install special equipment or instruments to conduct performance guarantee test on main equipments of this unit, which had been running continuously at full load since March 31.

The team of experts for fixing the equipments or instruments and for conductance of performance guarantee tests has already reached the project site.

He also said that the 300 MW unit-II is presently running at about 125 MW since April 16, 2008. The load of this unit will progressively be raised to full load, that is 300 MW by mid May as per technical specifications and in view of the other performances, he added.

UNI XC JN BJR PM1822

For Daily Alerts
Get Instant News Updates
Enable
x
Notification Settings X
Time Settings
Done
Clear Notification X
Do you want to clear all the notifications from your inbox?
Settings X
X