Bengaluru's MG Road metro develops faulty structure; BMRCL seeks 10 days to fix

|
Google Oneindia News

Bengaluru, Dec 14: After reports of structural fault in one of the pillars between the MG Road and Trinity Circle Metro Stretch, Bangalore Metro Rail Corporation Limited (BMRCL) has sought for about 10 days for the entire work to be completed. A team of engineers are working overnight to resolve the issue.

Bengalurus MG Road metro develops faulty structure; BMRCL seeks 10 days to fix

Due to the damage in one of the viaducts, trains have been slowing down to the minimum possible speed near the metro stations.

However, at pillar no 155 near the Trinity station, it was evident that the problem was not just about honeycombs.

Now, Bengalureans can travel in metro on Sundays from 7 amNow, Bengalureans can travel in metro on Sundays from 7 am

Bangalore Metro Rail Corporation (BMRCL) Managing Director Ajay Seth said that the corporation may require at least five to six days to complete the repair.

Deccan Herald quoted Ajay Seth, Managing Director of BMRCL, as saying, "The repair work can be completed in just two days. But, the preparation itself requires about 5 to 6 days. Our engineers are already busy installing the steel platform supported by stilts to carry out the repairs. Further, technical experts will decide on the future course of action."

For Daily Alerts
Get Instant News Updates
Enable
x
Notification Settings X
Time Settings
Done
Clear Notification X
Do you want to clear all the notifications from your inbox?
Settings X
X