BGR Energy systems wins turnkey contract for 500 MW plat in AP

Subscribe to Oneindia News

BGR
Mumbai, Feb 27: BGR Energy Systems Ltd has secured a Turnkey contract from Andhra Pradesh Power Generation Ltd (APGENCO) for the execution of Balance of Plant (BOP) for the ninth 500 MW unit in Stage VI of the Kothagudem Thermal Power Station valued at Rs 793 crore.

The contract scope of work includes designing, engineering, procurement and construction of complete mechanical, electrical, instrumentation and plant civil works for project, to be executed over a period of 26 months, the company informed the BSE.

BGR Energy has emerged as the largest EPC contractor of Power Plant BOP in the Country for large Power Plants of 500 MW and above. The company is currently executing three BOP contracts for 500 MW capacity coal-based power projects and this contract is the fourth contract. The current order book of the Company is Rs 3715 Crore.